User Rating: 
0
No votes yet

Project Summary

The Northcoast Regional Land Trust (NCRLT) has worked to restore historical tidal flow and native vegetation to the Wood Creek Tidal Marsh. Over the past 150 years, this site has been altered by diking and removal of vegetation and large woody debris. Despite these alterations, surveys have shown that endangered and threatened fish species utilize this area for rearing. The Wood Creek Tidal Marsh Enhancement Project’s primary climate change benefit comes in the form of flood mitigation for the lower Wood Creek/Freshwater Creek area. Anticipated increases in winter precipitation will likely bring increased flooding to the local watersheds. The reconnection of Wood Creek to Freshwater Creek through opening (and eventual removal) of the tidegate and creation of a more complex wetland channel system will expand the flow capacity of the project area, thereby reducing the velocity and shear potential of flood flows.

Project Background

The NCRLT owns and manages the 54-acre Freshwater Farms Reserve located on diked former tidelands along Humboldt Bay. This property is found in an area historically dominated by salt marsh but which has been converted into drier land for agriculture through diking and simplification of the slough systems. The project site itself was cut off from the greater Freshwater Slough system by a wooden flap tide gate and a levee, preventing tidal influence on the property. This site has been greatly altered over the past 150 years by diking, vegetation removal, and removal of large woody debris but still provides important habitat for juvenile salmonids. Surveys showed that endangered and threatened fish species, including coho salmon and steelhead and coastal cutthroat trout, have still been using this area for rearing prior to their migration to the ocean. Additionally, the endangered tidewater goby was discovered on the site. It was determined that expansion and enhancement of this habitat would be beneficial to these species and contribute to their recovery. In 2006, NCRLT, in partnership with the Redwood Community Action Agency – Natural Resource Services Division, initiated the development of this habitat restoration project. 

As lands are converted to salt marsh, there is an element of flexibility within and just outside the project area in regard to wetland plant community migration that may come with changes in the tidal levels and corresponding salinities and inundation rates at different elevations. While the plant species at the site are currently made up of a mix of salt-tolerant and freshwater wetland plants, the less salt-tolerant plant species may move up in elevation and back out of the lower project area, near the confluence of Wood Creek and Freshwater Creek, as sea level rise results in increased salinity and inundation of the lower elevations within the project area. The configuration of the project area and the adjacent wetland pasture area allows for this natural migration to occur without significantly affecting the objectives of the restoration project or the mixed agricultural land use on the 54-acre NCRLT property.

Project Implementation

The primary management objective for the property is to restore approximately 35 acres to its ancient tidal hydrology and create estuarine conditions on approximately 15 acres. The construction phase of the restoration project began on August 25, 2009, and took two and a half weeks to complete. Fish screens were installed on August 24 and California Department of Fish and Game biologists manually removed all fish from the project area prior to any construction. Four slough networks of varying complexity and totaling about 3,200 feet in length were excavated in the historic marsh plain.

Two existing seasonal ponds were also excavated to provide year-round habitat for tidewater goby (Eucyclogobius newberryi). It is hoped that tidewater goby known to inhabit the existing pond south of the Wood Creek tide gate will migrate through the new slough system and utilize these newly-excavated brackish water pools. A large pool was also excavated upstream of the crossing on Wood Creek in order to expand the freshwater habitat in which numerous young salmon have been observed. An existing dike on the north bank of Wood Creek (approximately 300 feet long) was removed to allow unimpeded tidal flow on the lower Wood Creek marsh plain.

The soil created from all of the excavation work was used on-site to construct shallow hills (hummocks) on the marsh plain. The hummocks were designed and constructed to only rise in elevation to where brackish wetland characteristics (e.g. frequent tidal inundation, specific plant communities) exist. Three redwood root wads were installed in the banks of the slough channels, while one root wad was placed in the large upstream freshwater pond. Five additional root wads were placed across the marsh plain within the project area to provide perches for the numerous raptors and wetland birds found in the area. Hand seeding with sterile erosion-control grass seed was done after construction to protect newly-constructed and unvegetated hummocks from tidal and raindrop erosion during the winter.

Two hummocks will remain unvegetated and will act as controls to help the project team determine the extent and profile of passive wetland plant colonization over time. The test hummocks will be surveyed annually and will be controlled for invasive plant species, which will be manually removed when observed.

The existing wooden flap tide gate at the mouth of Wood Creek was opened with a come-along in October 2009, allowing full access to the project site for fish, crustaceans, and other aquatic species, as well as the tides that bring these animals into the area. NCRLT staff will also observe the reaction of the project site to regular tidal inundation. Once the Project Manager and Project Engineer agree that the restoration site has settled, the tide gate will be dismantled in place and removed.

The revegetation phase for this project began on March 31, 2010, and was completed on June 19, 2010.  Thirty-eight thousand native wetland-associated plants were planted across the constructed tidal hummocks and along the margins of the new slough channels. The revegetation plan was developed to mirror natural conditions at neighboring Fay Slough.

Project Outcomes and Conclusions

These activities are expected to improve rearing success of salmonids and other living aquatic resource populations, as they expand and utilize the restored backwater habitat within a two-year period. NCRLT has engaged the local community in these restoration efforts through their education and outreach program “Building Community for Conservation.” This program includes interpretive hikes, K-12 education programs, canoe trips, and restoration activity days at the site.

Project Keywords

Recommended Citation

Feifel, K. (2010). Northcoast Regional Land Trust: Wood Creek Tidal Marsh Enhancement Project [Case study on a project of the Northcoast Regional Land Trust]. Product of EcoAdapt's State of Adaptation Program. Retrieved from CAKE: http://www.cakex.org/case-studies/northcoast-regional-land-trust-wood-cr... (Last updated August 2010)